€40,000,000
Timeline
Dec 23, 2021 – Dec 30, 2027
About this project
The Project includes rehabilitation measures to be carried out at the Fierza hydropower plant (HPP) in northern Albania. Fierza HPP is one of the three large state-owned hydropower plants along the Drin Cascade: Fierza, Komani and Vau I Dejes. With an installed capacity of 500 MW and an average annual generation of 1,328 GWh, it generates about a quarter of the domestically generated electricity. There have been insufficient investments in the states power generation infrastructure in recent decades, with the result that important maintenance and expansion investments have not been made. The Fierza HPP was built more than 40 years ago and is now in a precarious condition, sometimes causing supply shortages with significant negative effects on the economy. Generation losses have to be compensated by expensive electricity imports from abroad and additional greenhouse gas emissions. The project is expected to address the most pressing problems regarding two severely outdated turbines and four generators and thus lead to an extension of the HPPs lifetime by at least 30 years as well as to an increase in the HPPs reliability, efficiency and capacity. The investment will ultimately make a positive contribution to ensuring that households and businesses can be reliably and cost-effectively supplied with electricity and that high electricity import prices do not have an increasing impact on either end-user prices or the state budget, thus weakening the current account balance. The p…
Goals
Sustainable Development Goals this project works towards
Published details
View source- Published by
- Bundesministerium für wirtschaftliche Zusammenarbeit und Entwicklung (BMZ) · Government
- Countries
- Albania
- Sectors
- Hydro-electric power plants
- Focus
- Climate mitigation · Main focus
- Places
- Tirana
Documents and links
- www.kfw-entwicklungsbank.de/ipfz/Projektdatenbank/Elektro-Mechanische-Rehabilitierung-Des-Wasserkraftwerkes-Fierza-Dkti-46741.htm
- www.kfw-entwicklungsbank.de/Internationale-Finanzierung/KfW-Entwicklungsbank/Evaluierungen/Ergebnisse/
- www.kfw-entwicklungsbank.de/International-financing/KfW-Development-Bank/Evaluations/Results/
- www.gtai.de/KfW-Ausschreibungen
- www.gtai.de/kfw-tender
Published by Bundesministerium für wirtschaftliche Zusammenarbeit und Entwicklung (BMZ) to the International Aid Transparency Initiative (IATI), last updated 31 Aug 2026 and imported automatically. IATI identifier: DE-1-201969401.
Support Electro-mechanical rehabilitation of HPP Fierza
Donations through Solarpunk Taskforce are coming soon. Until then, follow the project to get its updates and share it with people who might help.
Updates
No updates yet.